Creating a task with duration in hours per day
Hi Team,
I am using zoho project for project management. In my organization there can be multiple projects running simultaneously. Also one employee can be work on two or more project. Now I want to assign one employee to two projects by dividing his one days work in 4 hours for one project and another 4 hours for second project. There is no provision for assigning task as above mentioned way.
When I assign more than one task to one employee, my resource allocation graph is showing my employee is overloaded but actually he is not.
I want solution for the above problem. Without fixing this problem I am not able to do my resource planning by using zoho projects.
Regards,
Sagar