Dependency View in Project Templates
I'm trying to set up some project templates but methinks there's a better way to set these up. The task dates in the project templates all need to have hard dates and there is no dependency view. Task dependency is most needed in these templates so we can have all dates and deadlines build off of one task (i.e. launch date... create account is 3 days after launch, qa is 2 weeks after launch) etc. As is we still have to go in and assign dates for every tasks when we use the project template!
Another cool idea would be to have task templates assigned to roles (project manager, account manager, accounting, etc) and then be able to assign people to specific roles. Since you have this in Zoho People, it would be great if you could use roles from Zoho People to assign tasks based on role vs specific people.
Dan Golden