Hours in Resource Allocation
Dear all,
It seems like the hours used in the resource allocation feature does not always match the number on the actual task. The problem seems to be that full time tasks (which is defined as 8h per day, 5 days per week in my system) are correctly calculated in the task view but in the resource allocation view, the task size is 24 hours per day. This causes heavy over-allocation.
Any clues on this behavior?
Best Regards
Johan
EDIT: See attached files. In the first file, the task shows up as a 24h task, even though it's clearly a 8h task (second file).