Task Dependancy

Task Dependancy

Hi,

I would like a why to setup a project that has dependancies that are relative to each other.

For example, if I have the following task list:

1 Assemble menu - Start Date Feb 20, 2009
2 Determine needed ingredients - Duration = 1 day, dependancy = 1
3 Build Shopping List - Duration = 1 day, dependancy = 2
4 Go Shopping -Duration = 1 day, dependancy = 3

From this, Zoho Projects should be able to automatically determine that:
Task 2 starts on Feb 21
Task 3 starts on Feb 22
Task 4 starts on Feb 23

Also, if Task 1's start date is delayed, all the other tasks should automatically adjust based on the new start date.

And if Task 2 runs long then zoho projects should be able to show a task's planned start date and actual start date based on the slippage.

Is any or all of this possible? If so, how?

Dave Curran




David Curran