Tasks Management and Timesheet
Hi guys. I am doing some testing to Zoho Projects and I realized that it won't work for me because I have to plan some tasks by the hours they actually will take and I just can't do that because when I create a task I have to specify a duration in days and the field only accepts integer values... However I can use the timesheet to assign time to tasks and I actually can set the hours spent for that task (and even minutes). Shouldn't the task feature and the timesheet feature match each other? How am I supposed to control planned task durations and real task durations when I assigned them to someone in my team? I think this is very importante for a project management tool such as this one.
sergio