Tasks with Varying Work Days

Tasks with Varying Work Days

Our company has task items that need to be scheduled with varying work days.

For example:
Project Management, Engineering and Manufacturing should only be scheduled Monday - Friday
Service needs to be scheduled Monday - Saturday
Shipping and Invoicing Terms need to be scheduled 7 days a week

in MS Project I can create a new "Calendar", edit the work days within that calendar, and then assign a task item to that calendar. This feature works very well for us. It allows us to properly schedule a project by accounting for each department's work schedule. is there a way to do this in ZOHO Projects?