Resource utilization report + Zoho People: wrong workload color?

Resource utilization report + Zoho People: wrong workload color?

Hello,
I use Projects + People in order to sync hourly and daily leaves and have a clear view of workload and available resources for each task.

I see the Resource Utilization report and the task creation start/due date calendar have different behaviors when showing the background color of the day based on the available working hours.

Here's a sample case for Friday 17th of Nov.:
  1. workday: 8 hours
  2. already allocated hours: 4:25
  3. taken hourly leave: 1 hour
  4. available hours for the 17th of Nov.: 8:00 - 4:25 - 1:00 = 2:35 hours
When looking at the resoruce utilization report, I see the day is marked in red even if the resource is in fact under-allocated:



When trying to add a task for the same date, I correctly see that the resource is under-allocated.



Is this the expected behavior? In case the answer is "yes" i think it would be better to standardize color usage as in the "Add task" calendar.

Thank you