Wouldn't it be better to make the 'task' a 'sum of subtasks'
Perhaps I have the wrong idea on tasks an subtasks, but shouldn't the task be a sum of subtaks. For instance:
- Clean the office (task)
- Clean windows (subtask)
- Clean tables (subtask)
- Clean coffee machine (subtask)
Currently when I add the task 'clean the office' and state that this takes 'one day' and add the subtasks with durations that equal 2, 4 and 2 hours respectively.
Now when I check the Gantt Chart or the Resource Utilization I see that I'm over-planned because I'm responsible for the Task and the Subtask.
I think it would be a better idea if the main task is a sum of subtasks :-).
Like to here opinions!