Use Duration and Start After to set time lead/lag for dependencies.

Use Duration and Start After to set time lead/lag for dependencies.

I've painstakingly built tasklist templates only to find that if you don't set lag-times, the time between your dependencies is not retained when you slide the predecessor tasks forward in the Gantt chart. My project has 25 tasklists, with ten dependencies each. That's 250 separate entries I need to make!

Surely there's a better way.

What if I could use the Duration and Start After times I've already set, and apply those to the lag times for dependencies? Even better if I could do this in bulk, or toggle it as a default setting.