Big vote for "hours" and duration driven dependencies
Hello folks,
i'd like to add my enthusiastic vote to add hours as duration units for tasks. Internet time is way too fast to count it by days. We definitely need hours.
And it seems like a simple fix since you already have time tracking logic built.
Please, please, we need "hours".
While you are at it. Please upgrade the dependency view to allow automatic date setting based on the duration and the date of the predecessor.
It seems unreasonable to ask users to manually change the dates of all tasks in the dependency chain when time line slips. Milestones are driven by dates, but tasks should be driven by effort/duration.
Thank you.