Changing Percent Complete doesn't change Status
When working thru the Task View on a project, I can use the Percent Complete dropdown list to indicate progress on the task. However, if the Status was Open and Percent is Zero, and I then change the Percent Complete to something other than Zero, the Status says as Open. How do I make the Status change to In Progress once the Percent Complete is greater than zero?