Completed subtask due date causes parent task to show overdue

Completed subtask due date causes parent task to show overdue

Scenario:
Open parent task has 3 subtasks
2 open subtasks have no due date
1 completed subtask has due date of 12/30/22 and completion date of 01/06/23

Bug: Parent task due date is locked to the completed subtask and shows as an overdue work item on the Home page

I understand that the subtask completion date was past the due date.  But, it has been marked complete.   Completed subtasks should not affect the due date of the parent task whether they were late or not.  It should no longer show as overdue in my opinion.