Dependency of tasks in hours
Dear all,
I create 2 tasks - each 1 hours of duration.
Task one is schedule DAY 1 on from 800 to 900.
Set dependcy of task 2 to start after task 1 is finished.
Expectation: both tasks will be completed day 1 (assuming resources are available).
Results... task 2 is scheduled from 900 to 1000.... DAY 2 (screen attached). Hours are ok... but where + 1 DAY came from?
Consequence:
I have project template where I have 50+ subsequent tasks and each task that takes 1 hrs is schedule for 1 day, thus project that should end within weeks is extended to months, thus making baseline basically useless.
What I do not understand or I am doing wrong? Is it how it is supposed to work? Or I am missing some settings?
Best Regards
Michael