Im new to zoho projects and i was wondering if there was a way to automatically move a task from a tasklist to another tasklist based on criteria such as when the task status is updated to completed and have it move to the tasklist that is named completed. In my case i want to move a task from graphic artwork to graphic artwork completed if the status is completed
For automation case as mentioned above, Custom Functions is the right solution. Using custom functions, we can move tasks from one task-list to another when the task's status is marked as 'Completed'. I've added the custom function code and help resources here for reference.
You need to establish a Connection to expand your Zoho Services’ third-party support and replace the exact Connection name in line no.6 within the given code. Refer to the below link to know more about Connections.
This is almost the same issue I have, but when I had someone try to help me create a custom function for it, it was to move a specific task to another project, which was not helpful at all. Let me know if you have figured it out.
You need to establish a Connection to expand your Zoho Services’ third-party support and replace the exact Connection name in line no.6 within the given code. Refer to the below link to know more about Connections.
For further clarification, please drop an email to us at support@zohoprojects.com.