Resource utilization report + Zoho People: wrong workload color?
Hello,
I use Projects + People in order to sync hourly and daily leaves and have a clear view of workload and available resources for each task.
I see the Resource Utilization report and the task creation start/due date calendar have different behaviors when showing the background color of the day based on the available working hours.
Here's a sample case for Friday 17th of Nov.:
- workday: 8 hours
- already allocated hours: 4:25
- taken hourly leave: 1 hour
- available hours for the 17th of Nov.: 8:00 - 4:25 - 1:00 = 2:35 hours
When looking at the resoruce utilization report, I see the day is marked in red even if the resource is in fact under-allocated:
When trying to add a task for the same date, I correctly see that the resource is under-allocated.
Is this the expected behavior? In case the answer is "yes" i think it would be better to standardize color usage as in the "Add task" calendar.
Thank you