Resources in Microsoft Project 2003 mpp files are not assigned to tasks during import

Resources in Microsoft Project 2003 mpp files are not assigned to tasks during import

Steps to reproduce:
  1. Create a new Zoho project.
  2. Assign user "boreilly" as a project user. There are now two users: current user and boreilly.
  3. Import an mpp file that contains two resources, current user and boreilly.
  4. During import, map both mpp resources to the respective Zoho users.
  5. Review the Zoho task list. Only current user is assigned any tasks. Tasks that had resource "boreilly" in the mpp file are unassigned in Zoho.