Task duration in hours with start date and end date
Hi,
Each of our tasks have a number of hours that the employee has to respect. But most of the tasks needs more days than what the system calculates. Is there a way to override the dates?
Let's say our project manager sends a design to be approved by the client. We create a task for 15 minutes but we give 3 days for the client to get back to us so the task should be 3 days with a duration of 15 minutes.
Another scenario is if I have a task of 40 hours for a programmer and I want to give her/him more than 5 days to complete it because we might need her/him on support that we can't really plan.
In a project template, you can specify dates and duration. That is perfect. But when the project is started, if you move a task, the days are not respected.
Can you help? I think this is basic project management and it's probably me that is missing something. Our old open source system (Web2Project) could do it.
Thanks.