How can I view critical path on the Gantt chart?

How can I view critical path on the Gantt chart?


Critical path can be viewed in the Chronology and Milestone Gantt.
  1. Navigate to a project.
  2. Select Gantt & Reports and select Gantt Chart.
  3. Click in the upper right corner.
  4. Toggle Critical Path and Slack to view them on the Gantt Chart.