There are three options to calculate project percentage completion.
Based on task and issue count - The project completion percentage is calculated based on the Open and Closed Status of both tasks and Issues.
Based on task completion percentage and issue count - The project completion percentage is calculated based on each task completion percentage. If there is no percentage completion in the issue module, status type (Open,Close) will be considered. In this type all tasks and issues will have equal weightage (Weightage = 1).
Based on weightage field - Users can customize the weightage for each task and issue. The project completion percentage is calculated based on the weightage value given in weightage field (numeric field or task duration or work hours).
Formulas to calculate to Percentage Completion:
Project Percentage Completion = (∑(Task Completion% * Task Weightage) + ∑(100% * Closed Issue Weightage)) / ( ∑ Task Weightage + ∑ Issues Weightage)
Milestone Percentage Completion = (∑(Task Completion% * Task Weightage) + ∑(100% * Closed Issue Weightage)) / ( ∑ Task Weightage + ∑ Issues Weightage)
Learn how to use the best tools for sales force automation and better customer engagement from Zoho's implementation specialists.
If you'd like a personalized walk-through of our data preparation tool, please request a demo and we'll be happy to show you how to get the best out of Zoho DataPrep.
You are currently viewing the help pages of Qntrl’s earlier version. Click here to view our latest version—Qntrl 3.0's help articles.