Task and Timesheet Settings | Online Help | Zoho Projects

Task and Timesheet Settings

Task Settings

Maintain Task Order

Enable this option to retain the order of tasks even when they are marked complete. Disabling this option will move completed tasks to the bottom of the task list.
  1. Click    in the top navigation panel.
  2. Navigate to Portal Configuration > Task & Timesheet > Task Settings tab.
  3. Toggle the Maintain Task Order setting to enable task order.

Task Prefix & ID

  1. Click    in the top navigation panel.
  2. Navigate to Portal Configuration > Task & Timesheet > Task Settings tab.
  3. Toggle the setting to enable/disable Task prefix and IDs.

Task Duration

  1. Click    in the top navigation panel.
  2. Navigate to Portal Configuration > Task & Timesheet > Task Settings tab.
  3. Scroll to the Task Duration section.
  4. Set the duration of tasks to either Days or Hours.
  5. Click Update.

Dependency Status

Task dependency status lets you know if a task is waiting for other tasks or is blocking other tasks from completion. There are two statuses, Waiting for and Blocking.

You can view the task dependency status in the classic, plain, Kanban view of tasks. The dependency status is also shown in the task details page. Tasks can be filtered by dependency status in the classic and plain view.

Resource Allocation

Resource allocation setting allows you to view a particular user's work allocation when assigning tasks. This setting is enabled by default.
  1. Click    in the top navigation panel.
  2. Navigate to Portal Configuration > Task & Timesheet > Task Settings tab.
  3. Scroll to Resource allocation under Task Settings.
  4. Toggle the setting to turn on resource allocation setting.

Associate Tasks with Issues

  1. Click    in the top navigation panel.
  2. Navigate to Portal Configuration > Task & Timesheet > Task Settings tab.
  3. Scroll the page and navigate to the Associate Tasks with Issues section. You can choose to receive Alerts about the associated Issues or not to receive alerts.
    1. When you select Do no show alerts, you can complete the tasks without receiving any alert messages about the associated Issues status.
  4. Click Update at the bottom of the page.

Task Dependency

You can configure the task dependency settings for your portal here. These options allow you to manage the shift in successor task every time the associated predecessor task is moved.
  1. Click    in the top navigation panel.
  2. Navigate to Portal Configuration > Task & Timesheet > Task Settings tab.
  3. Scroll the page and navigate to the Task Dependency section.
    1. Toggle the switch to enable or disable the setting. Explore more real time scenarios on the usage of task dependency settings here.
    2. Select a Default Dependency Type
      1. The dependency type that you select will be set between two tasks by default when you try to link them over the Gantt for the first time. However, the dependency type can always be modified at later stages.
  4. Click Update at the bottom of the page.
Note:
When selecting Automatic as the default dependency type, the dependency type will be assigned automatically based on the dates specified for the parent and child tasks. Automatic is most useful when you don't want to shift the dates for the child task.

Timesheet Settings

Log Hours for Tasks and Issues

You can now enable time logs for owned or all the tasks and issues.
  1. Click   in the top navigation panel.
  2. Navigate to Portal Configuration > Task & Timesheet > Timesheet Settings tab.
  3. Scroll to Log hours for Task and Issues section.
  4. Select Owned or All based on your preference.
  5. Click Update.

Log Hours for Closed Tasks and Issues

You can now enable time logs for closed tasks and bugs.
  1. Click    in the top navigation panel.
  2. Navigate to Portal Configuration > Task & Timesheet > Timesheet Settings tab.
  3. Scroll to Log hours for closed tasks and issues section.
  4. Select Allow or Don't allow based on your preference.
  5. Click Update.

 Time Log Restriction

  1. Click   in the top navigation panel.
  2. Navigate to Portal Configuration > Task & Timesheet > Timesheet Settings tab.
  3. Scroll to Restrict Time Log(s) section.
  4. Select Holiday, Weekend, or Leave based on your preference.
 Leave can be enabled only if your portal has Zoho People integration. Click here to learn more.

Timesheet Approval Settings

  1. Click    in the top navigation panel.
  2. Navigate to Portal Configuration > Task & Timesheet > Timesheet Settings tab.
  3. Scroll to the Timesheet Approval Process section.
  4. Set your approval process according to your preference.
  5. Click Update.

Multiple Timers Restriction

Restrict users from starting multiple timers in your portal.
  1. Click    in the top navigation panel.
  2. Navigate to Portal Configuration > Task & Timesheet > Timesheet Settings tab.
  3. Scroll to Multiple Timers Restriction.
  4. Select Allow or Don't Allow.
  5. Click Update.

Restriction Based on Work Hours

Time logs can now be restricted based on the work hours set for the task. If you allot 5 hours for a task, user cannot log more than 5 hours for that task.
  1. Click    in the top navigation panel.
  2. Navigate to Portal Configuration > Task & Timesheet > Timesheet Settings tab.
  3. Toggle the Time Log Restriction Based on Task Work Hours option.

Time Log Period Settings

Time logs are an effective way to track your users' hours. You can customize your past and future time-log settings, or even remove time logs entirely.

To customize your time log settings:
  1. Click    in the top navigation panel.
  2. Navigate to Portal Configuration > Task & Timesheet > Timesheet Settings tab.
  3. Scroll to the Time Log Period Settings section.
  4. Select Allow, Don't Allow, or Customize option for Log past time and Log future time functions.
  5. The restriction can also be applied when editing timesheets. Select the option Apply this restriction when editing timesheets (applicable only for Don't Allow and Customize options).
  6. Click Update.

Log Past Time

This setting determines whether to log past time.
Here are your options:

Allow

Log all past time

Don't Allow
Do not log past time
Customize

Allow past time logs for any specific length of time. Weekends and configured holidays will not be taken into account when selecting your time-log span.

For example:

-If you select 5 days before  09/19/2016, you will log time till  - 09/12/2016

-If you select 5 weeks before  09/19/2016, you will log time until 08/12/2016

-If you select 5 months before 09/19/2016, you will log time until 04/19/2016

Log Future Time

This setting determines whether to log future time.
Here are your options:

Allow
Log all future time
Don't Allow
Do not log future time
Customize

Allow future time logs for any specific length of time. Weekends and configured holidays will not be taken into account when selecting your time-log span.

Example:

-If you select 5 days from 09/19/2016, you can log time until 09/26/2016

-If you select 5 weeks from 09/19/2016, you can log time until 10/24/2016

-If you select 5 months from 09/19/2016, you can log time until 02/19/2017


The Time log settings will reflect in the following modules:

Affected modules
Relevant action
Affected module component
Bugs
Log hours for individual bugs.
Date picker
Task Details
Modifying log hours for individual tasks.
Date picker
Timesheet
 
  • Log Time

Logging time for a particular task/bug is added on a daily basis.

Date picker

 
  • Weekly Log Time

Logging time for a particular task/bug on a weekly basis.

Date picker


 
  • Calendar

Logging time  or editing an existing time log.

Date picker


 
  • Update Log Hours

Editing log entries.

Date picker

  

Example:

Joan wants to allow time-log entries for all past days while restricting entries to only two weeks in the future.

  1. Set the Past time-log to Allow- past days.

  2. Set the Future time-log to custom—2 weeks in the future

If the current date is 02/15/2017, all the users in the project will be able to log entries for all past days, and only until 03/01/2017 in the future. These settings will be reflected in all date pickers shown above.

Time log restriction

  1. Click    in the top navigation panel.
  2. Navigate to Portal Configuration > Task & Timesheet > Timesheet Settings tab.
  3. Scroll to Time Log Restriction and toggle to enable the setting.
  4. The Daily log hour limit and Weekly log hour limit are calculated based on business hours by default . You can edit the log hour limits as required.
    1. The daily log hour limit cannot exceed 24 hours and the weekly log hour limit cannot exceed 168 hours.
  5. Click Update at the bottom of the page.
Click to learn more about restrictions for timer.

Time Log Reminder

 The time log reminder can be used to remind users to update their daily and weekly time logs.
  1. Click   in the top navigation panel.
  2. Navigate to Portal Configuration > Task & Timesheet > Timesheet Settings tab.
  3. Scroll to Time Log Reminder and toggle to enable the setting.
  4. Set the time for Daily and Weekly Reminder based on your preference.
  5. Check the Notify running timers.
  6. Select the profiles or users to Exclude reminder for.
  7. Click Update.




See Also




    Zoho DataPrep Personalized Demo

    If you'd like a personalized walk-through of our data preparation tool, please request a demo and we'll be happy to show you how to get the best out of Zoho DataPrep.

    Zoho CRM Training

      Create, share, and deliver

      beautiful slides from anywhere.

      Get Started Now





              Zoho CRM Training Programs

              Learn how to use the best tools for sales force automation and better customer engagement from Zoho's implementation specialists.

              Zoho CRM Training

                  Zoho SalesIQ Resources



                      Zoho TeamInbox Resources




                                Zoho DataPrep Resources

                                  Zoho DataPrep Demo

                                  Get a personalized demo or POC

                                  REGISTER NOW


                                    Design. Discuss. Deliver.

                                    Create visually engaging stories with Zoho Show.

                                    Get Started Now











                                                          • Related Articles

                                                          • Task Dependency Settings

                                                            Configure task dependency settings and set default dependency type. Move up or extend dates of successor tasks or reschedule them based on completion date of predecessor task. Benefits: Move up dates of successor tasks if the predecessor task moves ...
                                                          • Timesheet Reports

                                                            Timesheet Reports Timesheet reports help you track the hours logged for tasks and issues. The Advanced Reports show the approved, rejected, and pending hours logged by each user. Billable and Non-billable Timesheet report shows how many hours are ...
                                                          • Task Templates

                                                            Add a Task List Template Click in the upper-right corner. Navigate to Customization > Task Templates. Click Create a Task List Template in the upper-right corner to add a new task list template.  Edit / Delete Task List Template Hover over the ...
                                                          • Timesheet Layouts & Fields

                                                            Zoho Projects supports custom fields and layouts for timesheets. Create your own fields and use them for customizing timesheets as per your business requirements. You can also associate a layout while adding time log. Click here to learn more about ...
                                                          • Task Reports

                                                            Task reports view provide a consolidated view of all the tasks in a project based on their status, milestone, priority, owner, and completion percentage. Benefits: Get the task count based on completion percentage View each user's tasks by percent ...

                                                          Resources

                                                          Videos

                                                          Watch comprehensive videos on features and other important topics that will help you master Zoho CRM.



                                                          eBooks

                                                          Download free eBooks and access a range of topics to get deeper insight on successfully using Zoho CRM.



                                                          Webinars

                                                          Sign up for our webinars and learn the Zoho CRM basics, from customization to sales force automation and more.



                                                          CRM Tips

                                                          Make the most of Zoho CRM with these useful tips.



                                                            Zoho Show Resources