Task Dependencies
Manage Task Dependency
Modify and remove task dependencies, and set lag or lead times from the List, Gantt, and Kanban views. Change dependency types, unlink dependencies, and adjust the time gap between tasks directly from each view's task details. Modify Task Dependency ...
Set Task Dependency
You can set task dependencies from the List, Gantt, and Kanban views. This includes adding predecessors and successors in the List view, connecting tasks in the Gantt view, and setting dependencies in the Kanban view. Set Task Dependency from List ...
Dependency Status
Users can view dependent tasks and their status (either Waiting for or Blocking ) in the task details page. If the dependency status in a task's detail page is shown as Waiting for, it means the task is waiting for other tasks to be completed before ...
Business Scenarios for Task Dependencies
Moving up Due Dates Scenario 1: In a construction site, the minimum time gap between curing the concrete (predecessor task) and painting the concrete (successor task) is expected to be 2 days (assumption). If curing is advanced before its scheduled ...
What is task dependency and what is it used for?
Some tasks need to be completed in a particular order. When the approach to a certain task depends on the result of another, dependency helps associate them together and determine an order to work. Projects' end-to-end Gantt visualization provides a ...