How to Track and Manage Schedule Changes in Zoho Projects

How to Track and Manage Schedule Changes in Zoho Projects

Keeping projects on track requires meticulous planning. However, unforeseen circumstances can cause changes to schedules, leading to delays. It becomes important to capture the reason for such changes to avoid them in the future.

Zoho Projects acknowledges this requirement by not only allowing users to track these changes, but also by mandating a valid reason when making such changes.

This can be achieved by using custom fields and layout rules in the task module.

First, we will create a multiline text field called Reason for Schedule change in the task layout. 



Next, we will create a conditional layout rule where the condition is a change in the start date of a task. 


Now, we can set an action where the Reason for Schedule change becomes mandatory when the start date is updated or modified.


This will ensure that whenever the start date of a task is changed, the Reason for Schedule change is required to be filled.

Do give this a try and let us know your thoughts in the comments below.






    • Sticky Posts

    • Automation Series: Auto-create Dependent Task on Status Change

      In Zoho Projects, you can automatically create and assign a dependent task when a task’s status is updated. This helps teams stay aligned, ensures reviews happen on time, and reduces manual effort. In this post, we’ll walk through an easy setup using
    • Time Log Reminder

      Tracking the time spent on tasks and issues is one of the most important functions of a timesheet. However, users may forget to update the time logs because they have their own goals to achieve. But, time logs must be updated at regular intervals to keep
    • Introducing the Zoho Projects Learning Space

      Every product has its learning curve, and sometimes having a guided path makes the learning experience smoother. With that goal, we introduce a dedicated learning space for Zoho Projects, a platform where you can explore lessons, learn at your own pace,
    • Update on V2 API End-of-Life Timeline

      Dear Users, Earlier this year, we shared the launch of the V3 APIs and requested users to migrate from the older V2 APIs by December 2025. We have received valuable feedback from our users and partners regarding their migration timelines. We are happy
    • Automation Series: Auto-update Phase Status

      Hello Folks! You can auto-update your phase's status based on status of underlying tasks using custom functions. In this series, we will showcase how to create and run custom functions, using Deluge, with ease. Follow the steps below and automate your