Importing from MSProject - Milestones are not recognised
Few problems:
- I had intended to use MS Project to develop my plans as I have used for years. The problem is that when I import the project, ZoHo Projects does not recognise the Milestones that have been created.
- It is quite normal to set certain Tasks as Milestones, how do I do this in ZoHo?
- There appears to be no correlation on the dates of the Milestones to the associated Tasks, how do I link this up so that the task dates drive the end date of the Milestones?
- How do I show the Critical Path in ZoHo Projects so I can manage end dates effectively?
Appreciate any feedback you can give me on these, I'm sure I must just not understand the logic in ZoHo.
Thanks,
Gareth
Zoho Desk Resources
-
Desk Community Learning Series
-
-
-
-
-
-
-
-
-
Sticky Posts
Tip: How to print the Gantt View
Though we move from the traditional project management system (using papers) to an online project management system, we still prefer to have a printed copy of the activities/tasks that are to be done in the project. This way, we can carry the to-do lists with us for the meetings and refer when we are offline. The print option, available at the right side of the page, allows the users to print the project information across all the modules. However, this option failed to print all the tasks & milestones
Project Management via Emails in Zoho Projects
We write mails to communicate. In Zoho Projects, we can write mails to collaborate. Yes, Zoho Projects supports Email based project management. The mails that you send turn into tasks, bugs, project comments, forum replies, etc. The following are some of the frequently asked questions that might be of some help to you. What are the pre-requisites to manage my projects through Emails? You need to have a personal / business mail ID that is registered and confirmed with accounts.zoho.com To learn more
Four types of task dependencies
"Nothing is particularly hard if you divide it into small jobs." - Henry Ford Projects, small or large, are driven by simple work units called tasks. Monitoring standalone tasks might look simple but as the workflow becomes elaborate, tasks may start relying on one another. In project management, this relationship between tasks is termed as "Task Dependencies". Dependency between tasks arise
Task and Project numbering
Zoho Projects now generates a unique number for each project, task, and issue added. The auto-generated ID is a combination of a prefix and a number which is assigned by Zoho Projects. The unique IDs for projects, tasks, and issues will be useful to track, identify, and search easily. You can modify the settings to enable or disable the Project and Task IDs. Learn more on how to modify Prefix & ID settings for projects and tasks. Issue IDs cannot be disabled, only its prefix can be changed (tasks
Task Inline Editing Enhancement
Hi All, Today, we have made an enhancement in task inline editing. In 4.0, task edit is moved in a single screen in a pop-up. We designed this in-order to make the task edit across the product to be the same. Let it be in Feeds, Tasks & My Tasks tab, Calendar & My Calendar tab, a click on the task title will open the popup and user can edit the values. Customers pointed us the inline editing was very useful to them & how much they miss that in 4.0. Based on the feedback, we have rolled out this enhancement.
Zoho CRM Plus Resources
Zoho Books Resources
Zoho Subscriptions Resources
Zoho Projects Resources
Zoho Sprints Resources
Zoho Orchestly Resources
Zoho Creator Resources
Zoho WorkDrive Resources
Zoho Campaigns Resources
Zoho CRM Resources
Writer Get Started. Write Away!
Writer is a powerful online word processor, designed for collaborative work.