can I build a schedule with dependency feature?
The dependency feature is very handy if you need to revise a schedule that you have created - however you cannot build a schedule that way because you can't assign a dependency until you assign a date to a task. That seems a little bit backwards - it would be more efficient and user friendly if you could create a project, in particular a project template, where you could establish the 1) tasks, 2) duration of each task, 3) and the dependencies for each task without assigning a date. Then when you use that template all you would have to do is input the start date and it would be built. The value of having dependencies, it seems to me, is that you don't have to touch every single task date assignment. Is this feature planned for 4.0 version or soon? I've seen very old posts dating back years talking about this, so I was surprised to see that it was not added for 4.0 - unless it is there and I've just not been able to find it.