Hello,
How can we change the default settings in Zoho Projects to never default the Work Hours when creating a task? The default seems to be Hours Per Work Day (9) * # of Days. Clearly the work effort is very different from the duration - for example, we may have a task that takes 4 hours but needs to be done over the next 5 business days. If the user entering the task forgets to change the Work Hours, then it will default to 45 hours, which then makes our resource utilization reports wildly inaccurate.
Thanks,
Jared