Enhanced dependencies

Enhanced dependencies

Hello,

For most simple projects the dependencies in Projects works well. 
  1. A task takes longer/shorter then planned and impacts all subsequent tasks
  2. Answering what-if scenarios, like adding additional resources or if there is a project delay
Projects can accommodate the above.  However, most of our project schedules can get complex and that is where Projects dependencies falls short in a couple of areas. 
  1. Ability to add a lag time to the dependency so that it is tied to the completion date of the predecessor but start a given amount of time before the end or after the end.  In the case of a negative lag, this allows overlapping of tasks that are dependent but not necessarily dependent on the completion.
  2. Scheduling the completion date of a task to finish the same time as another task.  A Finish to Finish dependency allows dependent tasks that must complete at the same time but have different durations.
We use both of these quite extensively in our project scheduling and without them it will cause of lot of extra work for our Project Mangers to manually schedule many of the tasks without using dependencies.

Regards,
Ron

    • Sticky Posts

    • Four types of task dependencies

      "Nothing is particularly hard if you divide it into small jobs."                                                                                                                  - Henry Ford Projects, small or large, are driven by simple work units called tasks. Monitoring standalone tasks might look simple but as the workflow becomes elaborate, tasks may start relying on one another. In project management, this relationship between tasks is termed as "Task Dependencies". Dependency between tasks arise
    • Tip: How to print the Gantt View

      Though we move from the traditional project management system (using papers) to an online project management system, we still prefer to have a printed copy of the activities/tasks that are to be done in the project. This way, we can carry the to-do lists with us for the meetings and refer when we are offline. The print option, available at the right side of the page, allows the users to print the project information across all the modules. However, this option failed to print all the tasks & milestones
    • Task and Project numbering

      Zoho Projects now generates a unique number for each project, task, and issue added. The auto-generated ID is a combination of a prefix and a number which is assigned by Zoho Projects. The unique IDs for projects, tasks, and issues will be useful to track, identify, and search easily. You can modify the settings to enable or disable the Project and Task IDs.  Learn more on how to modify Prefix & ID settings for projects and tasks. Issue IDs cannot be disabled, only its prefix can be changed (tasks
    • Task Inline Editing Enhancement

      Hi All, Today, we have made an enhancement in task inline editing. In 4.0, task edit is moved in a single screen in a pop-up. We designed this in-order to make the task edit across the product to be the same. Let it be in Feeds, Tasks & My Tasks tab, Calendar & My Calendar tab, a click on the task title will open the popup and user can edit the values. Customers pointed us the inline editing was very useful to them & how much they miss that in 4.0. Based on the feedback, we have rolled out this enhancement.
    • Blueprint in Zoho Projects

      Often, we stumble upon tasks having the same status workflow. Repetitive task processes are tedious to handle, right? That’s why we have introduced Blueprint for task automation. Blueprint is a tool to organize tasks and automate them based on the workflow you design and the criteria you define.    How do I associate tasks with a blueprint? You can set the criteria while creating the blueprint such that when you publish a blueprint, the tasks that satisfy the criteria will be associated with the