Power of Automation : Enhancing custom date field calculations by excluding Weekends and Holidays

Power of Automation : Enhancing custom date field calculations by excluding Weekends and Holidays

Hello Everyone,

A Custom function is a user-written set of code to achieve a specific requirement. Set the required conditions needed as when to trigger using the Workflow rules (be it Tasks / Project) and associate the custom function to it.

Requirement:

One of our customers has two date fields and is currently using a formula field to calculate the number of days between them. As per design, the default formula field includes weekends and holidays in the day count. However, the customer does not want weekends and holidays to be included in the calculation. This requirement was successfully achieved using Custom Functions along with Workflow rules.
 
Custom function code:
 
portalInfo = invokeurl
[
type :GET
connection:"XXXXX"
];
holidays = portalInfo.get("portals").get(0).get("settings").get("holidays");
holidayList = List();
for each  holiday in holidays
{
holidayList.add(holiday.get("date").toDate());
}
workingDaysList = date1.workDaysList(date2,{"Saturday","Sunday"},holidayList);
info "workingDaysList : " + workingDaysList.size();
param = Map();
param.put("days_between",workingDaysList.size());
updateProject = invokeurl
[
url :"https://projectsapi.zoho.com/api/v3/portal/" + portalId + "/projects/" + projectId
type :PATCH
parameters:param.toString()
connection:"XXXXX"
];
info "updateProject : "+updateProject;
return "success";
 
Make sure to replace XXXXX with Zoho Projects connection link name along with scopes: ZohoProjects.portals.READ, ZohoProjects.projects.UPDATE. Please find the screenshot of the list of parameters to be mapped for reference.
 
We hope you found this post useful. If you have any questions, feel free to share them in the comments below.

    • Sticky Posts

    • Time Log Reminder

      Tracking the time spent on tasks and issues is one of the most important functions of a timesheet. However, users may forget to update the time logs because they have their own goals to achieve. But, time logs must be updated at regular intervals to keep
    • Introducing the Zoho Projects Learning Space

      Every product has its learning curve, and sometimes having a guided path makes the learning experience smoother. With that goal, we introduce a dedicated learning space for Zoho Projects, a platform where you can explore lessons, learn at your own pace,
    • Update on V2 API End-of-Life Timeline

      Dear Users, Earlier this year, we shared the launch of the V3 APIs and requested users to migrate from the older V2 APIs by December 2025. We have received valuable feedback from our users and partners regarding their migration timelines. We are happy
    • Automation Series: Auto-update Phase Status

      Hello Folks! You can auto-update your phase's status based on status of underlying tasks using custom functions. In this series, we will showcase how to create and run custom functions, using Deluge, with ease. Follow the steps below and automate your
    • Automate Timesheet Approvals with Multi-level Approval Rules

      Introducing Approval Rules for Timesheets in Zoho Projects. With this automation, teams can manage how timesheets are reviewed and approved by setting up rules with criteria and assigning approvers to handle submissions. Timesheet, when associated to