Use case
Software development/ IT: You head a project management team, which is currently working on the task "Market Research". The next task would be "Product Development," which can only start if the current task is completed. For this case, you can set an FS (Finish to Start) dependency as default to organize the progress and enable the due date settings to provide flexibility to your team.
Event planner: An event organizing company organizes a birthday party. The decor team has arrived, and they plan to set the tables and chairs. However, before setting them, they need to lay the carpet on the floor. For this case, you can set an SS (Start to Start) dependency.
Construction: The client has requested to finish off the construction activity within April 2024. The house built should be painted before surrendering it to the client. To paint the house, scaffoldings have to be laid. This case, the dependency will be FF (Finish to Finish).