Recource Utilization

Recource Utilization


We use Recourse Utilization feature. It is almost the best tool a Manager can have. But it has a Major bug that many times make it useless.

The problem is especially in large tasks. For example 8hour work task but generally it a problem in every task. When u have planned 8 hours in a task and you have made 50% Completion Percentage this means that the task has 4 hours more to work. The problem is that the app does not calculate the Completion Percentage and keeps calcluating a split between days.
This is ok when you have done 50% of an 8 hour 2-day task in a day because next day calculates 4 hours left. But if 
you have completed 90% this means that you have left 1 hour for the next day. But in resource   Utilization the manager keeps seeing that the user is full of job. See the image bellow





We searched for a work around on it and we made a formula field calculating the hours that remain to complete the task as you can see in the image. But we can not make the table calculate it because it is not in hour side but totally backend.


I suggest that your team create a native Programme field to calculate remaining hours and this field to be the field used in your Backend to calculate Recourse Utilization.
I think that this bug is a major problem and i also believe that is not something very complicated for your team because you just have to change the calculation with jist another one number like. Something like this will do the job:
Remaining Hours to complete = (Hour estimation) - (Hour estimation*Completion Percentage)
Then u put this on the estimation and we will finally see the correct image of the work load.

Please anwser me and if this is possible make it a high priority fix because we can not use the tool
for the work it was designed.
If you make this change i think that this will be by far the best feature of ZOHO projects
 

      • Sticky Posts

      • Time Log Reminder

        Tracking the time spent on tasks and issues is one of the most important functions of a timesheet. However, users may forget to update the time logs because they have their own goals to achieve. But, time logs must be updated at regular intervals to keep
      • Enhanced Collaboration and Global Web Tabs

        Hello Users, We are rolling out two key enhancements in Zoho Projects that will be part of our November release. Here’s what to expect: 1. Collaboration Section in the Left Navigation Panel What’s new? All communication and interactive tools will be grouped
      • Tip 37: Time Log Restriction in Zoho Projects

        Timesheet in Zoho Projects helps you big time in entering log hours for the tasks and issues and approving them. Now, with the new Time Log Restriction option, you can set daily and weekly log hour limits. You can restrict users from entering extra log hours than the permissible limit. The limits are restricted to 24 hours per day and 168 hours per week by default based on business hours. To customize, navigate to Task & Timesheet settings under Portal Configuration in Zoho Projects setup and enable
      • Rename Task Module To Suit Your Project

        Task Module in Zoho Projects gives a comprehensive view of all the action items, known as Tasks, across all projects. However, different industries may use alternative terminology for similar processes, which might not always be recognised when labelled
      • Project Billing with the Staff Hours Method in Zoho Projects

        The Staff Hours Billing Method in Zoho Projects allows you to bill your clients based on the actual time spent by each team member on a project, at the rate set for each user. This is useful for projects where different skill sets are needed and service