Split Tasks Question for Zoho

Split Tasks Question for Zoho

Hello,

I am hoping Zoho can give me some advice on the best way to accomplish something in Zoho Projects. Please see attachment. In Microsoft Project it is possible to split a task into different time periods. This need is common in the construction industry.

As far as I can see the closest approximation of being able to split a task in Zoho Projects is to create a recurring task. The challenge with using recurring tasks instead of splits is we don't know in advance how a task needs to be split, so using recurring tasks doesn't really work. Rather, we need to initially create a task for say 160 hours, and then split the task later on as/if needed.

As an example, let's say we need to drywall 10 rooms. The contractor may have us drywall them all at once, or they may ask us to drywall 3 and then come back four weeks later and drywall the other 7. The possibilities are endless. So being able to split a task allows us to estimate the task, and then split it into meaningful chunks later as needed.

How would you advise I handle this in Zoho Projects? I am looking for suggestions.

Thank You!


      • Sticky Posts

      • Time Log Reminder

        Tracking the time spent on tasks and issues is one of the most important functions of a timesheet. However, users may forget to update the time logs because they have their own goals to achieve. But, time logs must be updated at regular intervals to keep
      • Enhanced Collaboration and Global Web Tabs

        Hello Users, We are rolling out two key enhancements in Zoho Projects that will be part of our November release. Here’s what to expect: 1. Collaboration Section in the Left Navigation Panel What’s new? All communication and interactive tools will be grouped
      • Tip 37: Time Log Restriction in Zoho Projects

        Timesheet in Zoho Projects helps you big time in entering log hours for the tasks and issues and approving them. Now, with the new Time Log Restriction option, you can set daily and weekly log hour limits. You can restrict users from entering extra log hours than the permissible limit. The limits are restricted to 24 hours per day and 168 hours per week by default based on business hours. To customize, navigate to Task & Timesheet settings under Portal Configuration in Zoho Projects setup and enable
      • Rename Task Module To Suit Your Project

        Task Module in Zoho Projects gives a comprehensive view of all the action items, known as Tasks, across all projects. However, different industries may use alternative terminology for similar processes, which might not always be recognised when labelled
      • Project Billing with the Staff Hours Method in Zoho Projects

        The Staff Hours Billing Method in Zoho Projects allows you to bill your clients based on the actual time spent by each team member on a project, at the rate set for each user. This is useful for projects where different skill sets are needed and service