DYK 7 - Set dependency from Gantt and List view

DYK 7 - Set dependency from Gantt and List view

Did you know task dependencies in Zoho Projects can be managed across different task views?

In a project, multiple teams work together towards the same goal but team members prefer accessing data with different perspectives depending on their responsibilities. The List view gives a granular view for users who work across multiple tasks, whereas the Gantt view helps users to plan visually and track progress across timelines. With Zoho Projects, task dependencies can be set from both the views, helping teams link tasks efficiently.

Let's assume a law firm that manages property purchases. The manager of the firm would prefer to use the timeline in the gantt view to create and plan tasks. While planning tasks, a Finish to Start dependency between tasks such as site inspection and document verification can be linked directly from the Gantt view by clicking and dragging a connection between the ends of two task bars. This ensures that any delay in site inspection automatically reschedules document verification, eliminating manual adjustments.

Gantt View

In the same case, as associates work through tasks in the List view, they can link tasks on the go by hovering over the task and entering the dependent task's ID or name in the Predecessor or Successor column. For tasks like seller background verification and property tax clearance that must be completed in parallel, a Finish to Finish dependency type directly from the List view can achieve this outcome enabling a structured process.

List View

The dependency type is automatically assigned based on the Default Dependency Type configured in the portal or project settings. If set to Automatic, the dependency type can be selected from the dropdown directly from the List view while linking tasks.
Notes
If the Predecessor or Successor column is not available by default in the list view, click on Notes and add the required columns.
As much as dependencies control task execution flow, task views influence how users view, set up, and modify them based on their needs.

Click this link to learn more about the different types of dependencies and when to use them. Have questions? Reach out to us support@zohoprojects.com.

    Access your files securely from anywhere

          Zoho FSM Video Tutorials


                All-in-one knowledge management and training platform for your employees and customers.






                                      Zoho Developer Community




                                                            • Desk Community Learning Series


                                                            • Digest


                                                            • Functions


                                                            • Meetups


                                                            • Kbase


                                                            • Resources


                                                            • Glossary


                                                            • Desk Marketplace


                                                            • MVP Corner


                                                            • Word of the Day


                                                            • Ask the Experts



                                                                      • Sticky Posts

                                                                      • DYK 14: Create Tasks with AI

                                                                        Did you know AI can suggest tasks within your Zoho Projects portal? Breaking a project into clear, actionable work items takes time and manual effort. Especially when the same team handles both planning and execution. AI task suggestions in Zoho Projects
                                                                      • Introducing CodeX Scripts for Custom Modules

                                                                        When a project involves processes beyond the usual modules such as tasks and issues, teams often create Custom Modules to keep information organized in a way that fits their workflow. Once those records become part of the process, there may also be specific
                                                                      • Create Custom Module Using AI in Zoho Projects

                                                                        Every team has its own way of managing work. While standard modules support common project management needs, many business processes require their own structure, fields, and terminology. With AI-powered Custom Modules in Zoho Projects, users can create
                                                                      • Collaborate Visually with Whiteboard in Zoho Projects

                                                                        Whiteboard in Zoho Projects allows you to collaborate visually by creating diagrams, annotating designs, and sketching project workflows using shapes, text, and images within project modules. Team members can work simultaneously, improving productivity
                                                                      • Create Flexible Layouts with Layout Rules

                                                                        In a project, when a work moves from planning to execution, the information teams need can change at every stage. A project can need one set of details, a phase can need another, and a custom process may require an entirely different set of information.


                                                                      Manage your brands on social media



                                                                            Zoho TeamInbox Resources



                                                                                Zoho CRM Plus Resources

                                                                                  Zoho Books Resources


                                                                                    Zoho Billing Resources

                                                                                      Zoho Projects Resources


                                                                                        Zoho Sprints Resources


                                                                                          Qntrl Resources


                                                                                            Zoho Creator Resources



                                                                                                Zoho CRM Resources

                                                                                                • CRM Community Learning Series

                                                                                                  CRM Community Learning Series


                                                                                                • Kaizen

                                                                                                  Kaizen

                                                                                                • Functions

                                                                                                  Functions

                                                                                                • Meetups

                                                                                                  Meetups

                                                                                                • Kbase

                                                                                                  Kbase

                                                                                                • Resources

                                                                                                  Resources

                                                                                                • Digest

                                                                                                  Digest

                                                                                                • CRM Marketplace

                                                                                                  CRM Marketplace

                                                                                                • MVP Corner

                                                                                                  MVP Corner






                                                                                                    Design. Discuss. Deliver.

                                                                                                    Create visually engaging stories with Zoho Show.

                                                                                                    Get Started Now


                                                                                                      Zoho Show Resources

                                                                                                        Zoho Writer

                                                                                                        Get Started. Write Away!

                                                                                                        Writer is a powerful online word processor, designed for collaborative work.

                                                                                                          Zoho CRM コンテンツ


                                                                                                            Nederlandse Hulpbronnen


                                                                                                                ご検討中の方





                                                                                                                          • Recent Topics

                                                                                                                          • Months of WooCommerce–Zoho Inventory sync failures and repeated support requests – has anyone experienced this?

                                                                                                                            Months of WooCommerce–Zoho Inventory sync failures and repeated support requests – has anyone experienced this? I run a small retail business using WooCommerce and Zoho One. For months, I have been trying to resolve recurring synchronisation failures
                                                                                                                          • Kaizen #263: Using Zoho CRM Skill to Build Widgets

                                                                                                                            Hello everyone! Welcome back to another exciting Kaizen post. In the previous Kaizen posts, we introduced the zoho-crm skill.md and explored how it can help with Zoho CRM APIs, Client Scripts, complex COQL queries, and Skill to build Queries. In this
                                                                                                                          • Zoho notebook No login

                                                                                                                            Hello Team, I recently downloaded and installed the latest version of zoho notebook for windows. But I am not able to login without providing any sso or email address. Did you removed the no login feature for this app? This is just a windows app. can
                                                                                                                          • Search is completely broken for PC

                                                                                                                            I go to note, try to search for "mtga" and it shows 702 results (it's a big note), highlights all letters "m" and I can't find anything. Same for "gathering" - it thinkgs I think only for "g". Looking for "zoho" shows as if I searched only for "z". Using
                                                                                                                          • Losing description after merging tickets

                                                                                                                            Hello, We merge tickets when they are about the same topic from the same client. It happens sometimes. We recently noticed that after the merger only the description from the master ticket is left in a thread. And the slave-ticket description is erased.
                                                                                                                          • Behind a great customer experience is a team

                                                                                                                            Hi everyone, October is here, and the first week marks the Customer service week. Each year, we thank our customer service professionals. Service professionals are all around us, even in our own workplaces: They handle essential administrative work like
                                                                                                                          • What's New - August and September 2026 | Zoho Backstage

                                                                                                                            Hello everyone, August and September bring a fresh wave of intelligence to Zoho Backstage. AI takes the spotlight with tools that help you create content, support attendees, and manage how AI fits into your events. Alongside AI, we’ve refined email communication,
                                                                                                                          • Images Not Displaying Properly in Zoho Desk

                                                                                                                            Hi, We are experiencing an issue with image rendering in Zoho Desk, affecting both incoming and outgoing emails. Images embedded in email conversations are not displaying properly. Instead, we see broken image icons or empty placeholders where the images
                                                                                                                          • Announcing the new SKILL.md for Zoho CRM and the updated OAS repository!

                                                                                                                            We are introducing a new zoho-crm skill to make working with Zoho CRM Developer tools (like APIs, functions, widgets, client scripts, queries etc) easier and faster, with the help of AI in your preferred AI harness like Claude Code, Codex, Cursor, VSCode
                                                                                                                          • Widget Height were destroyed

                                                                                                                            All widget heights in the Details Canvas view are broken. Moderation Update: This is a known issue with widget heights in Client Script popups and flyouts. A fix is in progress, and this post will be updated once it's released.
                                                                                                                          • Zoho Projects - Has something changed regarding to linking Projects and Deals via the API?

                                                                                                                            I am trying to link Zoho Projects to Deals in CRM using the API, but each time, the Deal Contact is added as a Client user and receives an email invite asking them to join the organisation. These are internal projects and the customer should not have
                                                                                                                          • How long does it take to review campaigns?

                                                                                                                            Hello Zoho, i scheduled my campaigns yesterday afternoon and it has been under review for over how many hours and those campaigns were supposed to be out yesterday so new ones can go out today. Is there something i'm doing wrong?
                                                                                                                          • Convert MSG to PDF in Bulk with Attachment Free

                                                                                                                            Microsoft Outlook saves each email as an MSG file, keeping with it key information like the sender, the recipient, the subject, the date, the body of the message, and any attachments. It can, however, be quite difficult to access a large number of MSG
                                                                                                                          • Using Mail Merge Template to Print Documents with One Subform Record's Fields per Document

                                                                                                                            Hello, We have a Mail Merge template created in Zoho Writer which is not able to perform the functionality which is currently required to automate the documentation task portion of our process. The CRM module we are primarily using is based on a "Loans"
                                                                                                                          • Convert MBOX to PST File Using Free Methods

                                                                                                                            MBOX is a mailbox format that is used by various email clients and services, such as Thunderbird, Apple Mail, Eudora, and Google Takeout. Yet, in order to be able to open your MBOX emails in Microsoft Outlook, you have to convert them from MBOX to PST
                                                                                                                          • Zoho Community Digest - September 2026 | Part 4

                                                                                                                            Hi everyone, and welcome back! The final week of September brought a revamped Books integration in Zoho CRM and Zoho Key Service for LLM access without API keys, Zoho Creator's audit trail becoming a full enterprise-grade auditing system, and Zoho One
                                                                                                                          • Automate weekly reports from Channels | Zoho Cliq AI use case #01

                                                                                                                            Scrolling endlessly through numerous threads in a Cliq channel and manually counting how many have been closed, how long people took to reply, and who actually participated can be tedious. After 20 minutes, you might have a number that no one can verify.
                                                                                                                          • Apple Mail to Outlook Converter - Export Apple Mac Mail to PST File

                                                                                                                            Apple Mail is a well-known email application among people who use Macs, whereas Microsoft Outlook is widely employed for both personal and business use. Should you decide to move from Apple Mail to Outlook, you'll probably need to transfer your mailbox
                                                                                                                          • Creator -Dynamic addition of Customer Portal User Licenses

                                                                                                                            Hi, We have a Creator App for B2C about to get released. We are experiencing the Portal User license challenge. Unable to predict the number of users who will download and Subscribe. When a User is about Subscribe and the portal licenses does not exists,
                                                                                                                          • Zoho Tables is now part of Zoho One!

                                                                                                                            Hey everyone! We've got some exciting news to share. Zoho Tables is now included in your Zoho One subscription at no extra cost. If you're already on Zoho One, head to your app list, add Zoho Tables, and get started right away. You don't need a separate
                                                                                                                          • How to import PST files in Office 365?

                                                                                                                            You can import PST files into Office 365 using native Outlook applications, the Microsoft Purview network upload method, or specialized third-party migration tools. Choosing the right method depends on whether you are migrating a single mailbox or executing
                                                                                                                          • [Webinar] Zoho CommunitySpaces MCP

                                                                                                                            New to MCP, or just exploring what's possible? Join us for a webinar on Zoho MCP and your community. We'll show you how Zoho CommunitySpaces and Zoho MCP work together, what your AI co-host can do inside your community, and how to get started. Register
                                                                                                                          • Solution to Import OST File into Office 365.

                                                                                                                            In today’s digital workplace, organizations are rapidly moving toward cloud-based email systems for better flexibility, security, and collaboration. Microsoft 365 has become one of the most widely used platforms for business communication. A common requirement
                                                                                                                          • Address limits per customer by edition

                                                                                                                            I’m on the Standard edition and have reached a limit of 30 addresses under a single customer. Before I move to an annual Professional subscription, I need to confirm the following: What is the maximum number of addresses allowed under one contact, and
                                                                                                                          • How can I show an uploaded image larger/full size in a Zoho Forms response PDF?

                                                                                                                            Hi,  I noticed that in a response PDF for Forms, the uploaded image is shown in a tiny box as seen in my screenshot. Is there any way I can make that appear larger in the response PDF? thanks.
                                                                                                                          • Live connection to DS files in Zoho Creator / ChatGPT

                                                                                                                            As an idea, we are using ChatGPT to build with Zoho Creator (outside of Zia), which is works brilliantly to assist write deluge, provide test suggesitons etc. Currently we are uploading the DS files which are very point in time, it would be great to have
                                                                                                                          • Meet PageHealth by Zoho PageSense: a free way to find out what's holding your page back

                                                                                                                            We all know the feeling. You've spent days tweaking headlines, moving buttons, and rewriting copy, and you're still not sure why visitors aren't sticking around. Revamping your website is hard, and figuring out what's actually getting in the way is even
                                                                                                                          • Export Exchange Online Archive Mailboxes to PST for Microsft 365 Users

                                                                                                                            With Microsoft 365 it is possible to archive older emails in Exchange Online in order to keep the main mailbox tidy. If however you need to export the archived emails to a PST file for the purposes of backup, migration, compliance or for use offline,
                                                                                                                          • Lookups and Custom Modules

                                                                                                                            I created a Custom Module that I'm calling "Item Purchasing Group". This module will store information for groups of Items that must be purchased together (including minimum overall quantities and/or values, etc.). This will have a one-to-many relationship
                                                                                                                          • Task Module quick create settings

                                                                                                                            Hello, requesting the Task module receive a quick create customization settings. We have added custom fields and have to select "More fields" at the bottom of the pop-up to access the custom fields.
                                                                                                                          • Your employees changed departments. Did your IT systems notice?

                                                                                                                            An employee joins your Marketing team. HR adds their details to the organization's user directory. The IT admin, in turn, creates their Zoho One account, assigns the required applications, adds them to groups and provides access based on the organization's
                                                                                                                          • AI Calling

                                                                                                                            Hi, does anyone have experience or any thoughts on AI Calling. Getting AI to make calls on behalf of your company. We are looking into it, but are finding it difficult to get info and providers that can assist.
                                                                                                                          • Zoho Books | Product updates | August 2026

                                                                                                                            Hello users, July has been an exciting month for Zoho Books! This month, we're excited to introduce HTML PDF Templates, Placeholders as Pills, expanded approval workflows for Sales Returns and Journals, and significant compliance updates across the India,
                                                                                                                          • Button or Links order

                                                                                                                            Is there a way to re-order the buttons or links that are created? Moderation Update: With our recent enhancement to custom button creation from the layout editor, administrators can now reorder custom buttons directly from the layout editor, and this
                                                                                                                          • Email Forwarding to Zoho Desk Failing After Migration from Gmail to Outlook (Microsoft)

                                                                                                                            We recently migrated from Gmail to Microsoft Outlook. Since the migration date, emails sent by our customers are no longer being received by Zoho Desk. I tried setting up the email forwarding rules in Outlook similar to what we had in Gmail, but it still
                                                                                                                          • Option to Disable Knowledge Base Section in Feedback Widget Popup Hello Zoho Desk Team

                                                                                                                            Hello Zoho Desk Team, How are you? We are actively using Zoho Desk and would like to make more use of the Feedback Widget. One of the ways we implement it is through the popup option. At the moment, the popup always displays the Knowledge Base section,
                                                                                                                          • How to Fix an Outlook OST File That Cannot Be Opened

                                                                                                                            Have you at any time attempted to open Outlook only to find that your OST file cannot be accessed? It can be very annoying, particularly since the file holds important emails, attachments, and other mailbox data. This problem might arise due to file corruption,
                                                                                                                          • Record positive and negative bank transactions in the same expense account

                                                                                                                            Hello, I hosted a promotional event and paid a vendor $600 for food catering (bento boxes). Twenty people attended the event, and each person paid $30 for a bento box, resulting in 20 separate $30 transactions deposited into the bank. I coded the $600
                                                                                                                          • Is it possible to log text messages from iphone into Zoho CRM

                                                                                                                            My team is more and more utilizing text messaging to communicate with clients. Does Zoho have a solution for logging these text messages when clicking "Send Text Message" from the Zoho app. Much like when you call, you get prompted to log a call, can
                                                                                                                          • CRM Address Field - States with Countries in brackets

                                                                                                                            Hi, Could you please remove the country in brackets from the Global State List, or at least allow us to edit these entries? It looks like the brackets were added during the initial data population, perhaps by someone building the list in a spreadsheet
                                                                                                                          • Next Page