Kanban burnup | Kanban Reports | Zoho Sprints Help

Kanban burnup

Burnup report

The burnup chart plots the item completion as the estimation points that are completed to represent the items on the board that have been completed. 



You can use this chart to:
  1. Track the completed estimation points on a daily basis.
  2. Know the total number of completed at the end of the day. 

What the report shows?

This report shows the completion of items as points achieved based on the completed items on the board.
  1. X-axis denotes the end dates of the items.
  2. Y-axis denotes the total estimation points based on the items on the board.

Insights

  1. You can view the completion of items based on the collected estimation points.
  2. You can view the completion of items based on the completed work item count.
  3. You can assess your progress based on the collected points.

Report table

The table below the report provides you with a summary view of completed and pending estimation points, along with the list of work items and their estimation points.
  1. The completed estimation points are marked (-).
  2. The reopened and newly added estimation points are marked (+).

Access burnup report

To access the report:
  1. Go to the kanban project.
  2. Select the Reports module.
  3. Select Burnup report type.
  4. Select View type.
    1. Points: Track based on completed estimation points.
    2. Count: Track based on completed work item count.
  5. Hover over the plotted points to view details.
  6. Click the plotted points or scroll down to navigate to the detailed table for the report.
Notes
Note:
You can export the reports in PDF and PNG formats for external use.
You can schedule exports to automate periodic export of the reports. Navigate to the Export History to access the exported files.
 

More Reads 
Kanban process time 
Item process time