Task Roll-Up

Task Roll Up in Projects  

Roll-Up helps you summarize project information, such as the overall project duration, planned work hours, actual log hours, and percentage completion. A project Roll-Up summarizes the total of the planned work hours of the project, the total of the actual hours logged in, the aggregate of the completion percentage based on all tasks in a project, and the overall project duration based on the start date of the earliest task and end date of the last task in the project. These details can also be rolled up to the milestones. Additionally, task work hours and log hours can be rolled up from their subtasks.
Example 1: Task A has two subtasks, C and D. When you log 4 hours for C and 3 hours for D, the log hours for the parent task are automatically calculated as 7 hours.

Example 2: Subtask C is scheduled between 1st October 2020 and 15 October 2020 and Subtask D is scheduled between 10th October 2020 and 30th October 2020. In this case Task A will be scheduled automatically between 1st October 2020 (which is the earliest start date among all its subtasks) and 30th October 2020 (which is the latest finishing date among all its subtasks. The start and end date of the milestones and the project as a whole will be calculated based on the start date of the earliest starting subtask and the end date of the latest finishing subtask.

Start date, end date, % completion, and budget (if enabled) will roll up from Subtasks > Tasks > Milestone > Projects. Work hours and log hours will roll up from Subtasks > Tasks
Feature Availability: Premium and Enterprise plans.

Can I disable Roll-up?

Since work hours and log hours are updated automatically from child tasks to parent tasks, disabling this feature and entering data manually will lead to inconsistencies and generate faulty reports. Hence, you will not be able to disable this feature after enabling it.

Roll-up is only applicable for the project it is enabled in and does not affect other projects in the portal.

 Enable Roll Up 

 Enable Roll-up While Creating a New Project 

  1. Click the Projects tab from the left navigation panel.
  2. Click the New Project button.
  3. Fill in the project details and check the Roll-Up option.
  4. Start date, end date, and % completion are rolled up from tasks/subtasks to milestones and project.
  5. Start date, end date, % completion, work hours, and log hours are rolled up from subtasks to tasks.
  1.  A dependent task cannot be made a subtask when roll-up is enabled. 
  2.  Dependencies cannot be set between subtasks and its parent when Roll-up is enabled. 
  3.  Strict Project start and end dates will not change with change in subtask dates. 
  4.  Subtasks start and end dates should fall within the date range of a strict project.

Enable Roll-Up While Editing New Projects

  1. Hover over your project in left navigation panel, click  and click Edit Project.
  2. Toggle on the ROLL-UP PROJECT under Project Information. (Enabling Roll-up when editing a project is available only for new projects.)
Roll-up cannot be enabled if there are dependencies between subtasks and their parent task.
Roll-up cannot be enabled if a parent task has work hours or log hours.
Roll-up cannot be enabled if tasks are imported in bulk.

Roll-Up Using Gantt Chart  

Start date, end date, and % completion can also be rolled up from tasks/subtasks to the milestones and projects in the Gantt chart.

For example, the Homepage Revamp, a subtask within the Website Redesign task, is extended by two weeks with new requirements. You can easily update the schedule in the Gantt chart.

Open Tasks in the Gantt view in your project, then extend the Homepage Revamp subtask's end date by dragging the bar two weeks later in the Gantt Chart.

This action triggers a roll-up effect: the Website Redesign task's end date automatically adjusts to include this delay. Consequently, the Website Launch milestone and the project timeline are updated to match the new earliest start and latest end date of all subtasks, accurately reflecting the delay in the project's Gantt chart.

Roll Up Log Hours of Subtasks  

Log hours are rolled up from subtasks to their parent tasks.
  1. Navigate to your Project, then click Tasks in the top band.
  2. Open the List view, then enter log hours in the Timelog Total column corresponding to the subtask.
  3. Alternatively, log hours for subtasks from the task details page.
  4. The Task's Timelog Total is automatically updated summing up the log hours of the subtasks.
For example, in the User Interface Design task, log 5 hours for Design Mockups and 8 hours for Prototype Development. The total logged hours for User Interface Design task automatically updates to 13 hours, summing the hours from both subtasks.

Roll-Up Work Hours of Subtasks  

Work hours are rolled up from subtasks to their parent tasks.
  1. Navigate to your Project, click Tasks in the top band.
  2. Open the List view, then enter the work hours column corresponding to the subtasks.
The Work hours of the task will be updated automatically by summing up the work hours of the subtasks.



    Zoho CRM Training Programs

    Learn how to use the best tools for sales force automation and better customer engagement from Zoho's implementation specialists.

    Zoho CRM Training
      Redefine the way you work
      with Zoho Workplace

        Zoho DataPrep Personalized Demo

        If you'd like a personalized walk-through of our data preparation tool, please request a demo and we'll be happy to show you how to get the best out of Zoho DataPrep.

        Zoho CRM Training

          Create, share, and deliver

          beautiful slides from anywhere.

          Get Started Now


            Zoho Sign now offers specialized one-on-one training for both administrators and developers.

            BOOK A SESSION








                                You are currently viewing the help pages of Qntrl’s earlier version. Click here to view our latest version—Qntrl 3.0's help articles.




                                    Manage your brands on social media

                                      Zoho Desk Resources

                                      • Desk Community Learning Series


                                      • Digest


                                      • Functions


                                      • Meetups


                                      • Kbase


                                      • Resources


                                      • Glossary


                                      • Desk Marketplace


                                      • MVP Corner


                                      • Word of the Day


                                        Zoho Marketing Automation

                                          Zoho Sheet Resources

                                           

                                              Zoho Forms Resources


                                                Secure your business
                                                communication with Zoho Mail


                                                Mail on the move with
                                                Zoho Mail mobile application

                                                  Stay on top of your schedule
                                                  at all times


                                                  Carry your calendar with you
                                                  Anytime, anywhere




                                                        Zoho Sign Resources

                                                          Sign, Paperless!

                                                          Sign and send business documents on the go!

                                                          Get Started Now




                                                                  Zoho TeamInbox Resources



                                                                          Zoho DataPrep Resources



                                                                            Zoho DataPrep Demo

                                                                            Get a personalized demo or POC

                                                                            REGISTER NOW


                                                                              Design. Discuss. Deliver.

                                                                              Create visually engaging stories with Zoho Show.

                                                                              Get Started Now







                                                                                            You are currently viewing the help articles of Sprints 1.0. If you are a user of 2.0, please refer here.

                                                                                            You are currently viewing the help articles of Sprints 2.0. If you are a user of 1.0, please refer here.



                                                                                                  • Related Articles

                                                                                                  • Task Automation within Task Module

                                                                                                    Automate repetitive tasks and streamline workflows within the Tasks module without the need to navigate away from the screen.With workflow rules, you can define conditions and actions to automatically trigger specific actions based on predefined ...
                                                                                                  • Task Custom View

                                                                                                    Task Custom View is an option to customize and filter your tasks based on specific criteria. For example, if an employee is assigned to the design department, they can customize their view to see all the tasks specific to the design department. ...
                                                                                                  • Task and Task Lists

                                                                                                    Can I carry forward dependencies from task list templates when I create a new task list? You cannot set dependencies in task templates. However, you can set dependencies in Project templates. When you create a new task list select Choose from project ...
                                                                                                  • Task Templates

                                                                                                    Add a Task List Template Click in the upper-right corner of the top navigation band. Navigate to Customization > Task Templates. Click Create a Task List Template in the upper-right corner to add a new task list template. Edit / Delete Task List ...
                                                                                                  • Task Settings

                                                                                                    The Task Settings under Project Configuration lets you modify the default settings at a project level. This will override the portal level setting for a particular project alone. Click in the top navigation panel. Navigate to Project Configuration > ...
                                                                                                    Wherever you are is as good as
                                                                                                    your workplace

                                                                                                      Resources

                                                                                                      Videos

                                                                                                      Watch comprehensive videos on features and other important topics that will help you master Zoho CRM.



                                                                                                      eBooks

                                                                                                      Download free eBooks and access a range of topics to get deeper insight on successfully using Zoho CRM.



                                                                                                      Webinars

                                                                                                      Sign up for our webinars and learn the Zoho CRM basics, from customization to sales force automation and more.



                                                                                                      CRM Tips

                                                                                                      Make the most of Zoho CRM with these useful tips.



                                                                                                        Zoho Show Resources