Task Dependency - Predecessor and Successor Task Columns in the List View
Task Dependency establishes connection between multiple tasks. It specifies the sequence in which tasks must be completed before other tasks can commence. While the
Gantt chart in Zoho Projects provides visual representation of
task dependencies, users can also access and manage dependencies from the Classic and Plain list view: the Predecessor and Successor columns can be enabled from either of these views. Users can set dependencies by clicking on the respective column and adding the dependent task ID.
In this example, we are setting the task having ID DC-T239 as a predecessor for the Slab Inspection task. FS denotes the
dependency type Finish-Start, and +3 adds
lead time. On saving, the successor column against the task DC-T239 will display the ID of the Slab Inspection task automatically. This establishes the dependency between the two tasks.
Please refer to our
help document for additional information regarding this feature. You may also send an email to
support@zohoprojects.com or leave a comment below if you have questions.
Sticky Posts
Time Log Reminder
Tracking the time spent on tasks and issues is one of the most important functions of a timesheet. However, users may forget to update the time logs because they have their own goals to achieve. But, time logs must be updated at regular intervals to keep
Enhanced Collaboration and Global Web Tabs
Hello Users, We are rolling out two key enhancements in Zoho Projects that will be part of our November release. Here’s what to expect: 1. Collaboration Section in the Left Navigation Panel What’s new? All communication and interactive tools will be grouped
Tip 37: Time Log Restriction in Zoho Projects
Timesheet in Zoho Projects helps you big time in entering log hours for the tasks and issues and approving them. Now, with the new Time Log Restriction option, you can set daily and weekly log hour limits. You can restrict users from entering extra log hours than the permissible limit. The limits are restricted to 24 hours per day and 168 hours per week by default based on business hours. To customize, navigate to Task & Timesheet settings under Portal Configuration in Zoho Projects setup and enable
Rename Task Module To Suit Your Project
Task Module in Zoho Projects gives a comprehensive view of all the action items, known as Tasks, across all projects. However, different industries may use alternative terminology for similar processes, which might not always be recognised when labelled
Project Billing with the Staff Hours Method in Zoho Projects
The Staff Hours Billing Method in Zoho Projects allows you to bill your clients based on the actual time spent by each team member on a project, at the rate set for each user. This is useful for projects where different skill sets are needed and service