Hi Zoho Team,
We´re using Zoho Projects to manage the opening process of our stores. Since the opening process is basically the same for almost all the stores, we decided to create a template as the base of all the opening projects.
We at first created a project, set the initial and due date, the dependency and get every task asigned. Later we created a template based on this project.
Entering the template, we noticed that "start after" column has no value, we thought it could because of the first task has no predecessor(the only one). So we set the correct "start after" days and after refresh the page, all the tasks had a "start after" days value.
But here comes the problem:
some tasks had the correct "start after" value and some not.
Later we´ve tried several times and this issue just keeps appreared. Since our projects had began already, we manually sett all the "start after" values in the template with the correct days.
This week, we´re creating another template and again this issue apprears.
We´d like know if we did something wrong on creating the template?
Thanks a lot in advance,
Yong