Hello Everyone,


A custom function is a software code that can be used to automate a process and this allows you to automate a notification, call a webhook, or perform logic immediately after a workflow rule is triggered. This feature helps to automate complex tasks and calculations.


Lets take the below requirement from a customer - 


A customer would like to monitor the progress of current week & last week tasklists and update in the custom fields at Milestone and projects levels.

Lets say, there are 4 Tasklists under a Milestone, the current week progress of these four Tasklists should be updated in the custom field of associated Milestone. Likewise, the progress of the previous week should be populated in another custom field.


Similarly, it should be rolled up and displayed in a custom field at Project level.


A custom function can be used to fulfil this need. However, this has to be implemented for each project i.e. ID of the project should be passed directly in the arguments. I have attached the screenshots of Arguments & schedule.


Establishing a connection with the scopes "zohoprojects.milestones.ALL , zohoprojects.projects.ALL" is all that is required. Below link will let you know how to establish a connection.


https://help.zoho.com/portal/en/kb/projects/integration/connections/articles/connections-23-5-2022#How_to_establish_a_Connection


endPoint = "https://projects.zoho.com/restapi/portal/";

endPointV3 = "https://projects.zoho.com/api/v3/portal/";

// project cf id

projectCurrentWeekCustomFieldName = "xxxxxx"; // project current week cf name

milestoneCompletionPercent = 0;

divideBy100 = 0;

isTrue = false;

projectCurrentWeekValue = 0;

getAllMilestones = invokeurl

[

url :endPoint + portalId + "/projects/" + projectId + "/milestones/"

type :GET

connection:”******”

];

for each  milestone in getAllMilestones.get("milestones")

{

milestoneId = milestone.get("id_string");

getMilestoneDetails = invokeurl

[

url :endPointV3 + portalId + "/projects/" + projectId + "/milestones/" + milestoneId

type :GET

connection:”******”

];

CurrentWeekFieldId = "xxxxxxx";

// milestone cf id

LastWeekFieldId = "xxxxxx";

// milestone cf id

milestoneParameter = Map();

if(getMilestoneDetails.get("custom_fields").get(CurrentWeekFieldId).get("value").equalsIgnoreCase("-"))

{

milestoneParameter.put(CurrentWeekFieldId,getMilestoneDetails.get("completion_percent").toString());

isTrue = true;

}

else

{

milestoneParameter.put(LastWeekFieldId,getMilestoneDetails.get("custom_fields").get(CurrentWeekFieldId).get("value").toString());

milestoneParameter.put(CurrentWeekFieldId,getMilestoneDetails.get("completion_percent").toString());

}

milestoneCompletionPercent=milestoneCompletionPercent+getMilestoneDetails.get("completion_percent");

divideBy100 = divideBy100 + 100;

updateMilestoneDetails = invokeurl

[

url :endPointV3 + portalId + "/projects/" + projectId + "/milestones/" + milestoneId

type :POST

parameters:toString(milestoneParameter)

connection:"*********"

];

}

projectMilestoneCompletionPercentage = (milestoneCompletionPercent / divideBy100) * 100;

// Update Project

projectCurrentWeekFieldId = "xxxxxx";

// project cf id

projectLastWeekFieldId = "xxxxxxx";

projectsParameter = Map();

if(isTrue)

{

projectsParameter.put(projectCurrentWeekFieldId,toString(projectMilestoneCompletionPercentage));

}

else

{

getProjectResponse = invokeurl

[

url :endPoint + portalId + "/projects/" + projectId + "/"

type :GET

connection:"*********"

];

customFields = getProjectResponse.get("projects").get(0).get("custom_fields");

for each customField in customFields{

if(customField.containKey(projectCurrentWeekCustomFieldName)){

projectCurrentWeekValue = customField.get(projectCurrentWeekCustomFieldName);

}

}

projectsParameter.put(projectLastWeekFieldId,projectCurrentWeekValue);

projectsParameter.put(projectCurrentWeekFieldId,toString(projectMilestoneCompletionPercentage));

}

updateProjectResponse = invokeurl

[

url :endPoint + portalId + "/projects/" + projectId + "/"

type :POST

parameters:projectsParameter

connection:"***********"

];


Creating custom functions in Zoho Projects is straightforward and well-documented. Watch this space for more such custom function codes. 


    Zoho Desk Resources

    • Desk Community Learning Series


    • Digest


    • Functions


    • Meetups


    • Kbase


    • Resources


    • Glossary


    • Desk Marketplace


    • MVP Corner


    • Word of the Day


      • Sticky Posts

      • Tip 37: Time Log Restriction in Zoho Projects

        Timesheet in Zoho Projects helps you big time in entering log hours for the tasks and issues and approving them. Now, with the new Time Log Restriction option, you can set daily and weekly log hour limits. You can restrict users from entering extra log hours than the permissible limit. The limits are restricted to 24 hours per day and 168 hours per week by default based on business hours. To customize, navigate to Task & Timesheet settings under Portal Configuration in Zoho Projects setup and enable
      • Rename Task Module To Suit Your Project

        Task Module in Zoho Projects gives a comprehensive view of all the action items, known as Tasks, across all projects. However, different industries may use alternative terminology for similar processes, which might not always be recognised when labelled
      • Project Billing with the Staff Hours Method in Zoho Projects

        The Staff Hours Billing Method in Zoho Projects allows you to bill your clients based on the actual time spent by each team member on a project, at the rate set for each user. This is useful for projects where different skill sets are needed and service
      • Achieve Full Financial Control by Tracking Both Cost Budget and Budgeted Hours

        Zoho Projects now supports tracking budget with both Cost Budget and Budgeted Hours simultaneously across all modules (Based on Project, Phase, Task, or User). Why Track Both? Tracking both cost budget and budgeted hours provides a more holistic view
      • 🎉 Celebrate Zoho Projects’ 18th Birthday with Us! 🎉

        Hello Zoho Projects Community, We’re thrilled to announce that Zoho Projects is turning 18 today! To mark this milestone, we’re hosting a special AMA (Ask Me Anything) event starting at 3 PM IST today and running until 3 PM IST tomorrow. This is your

      Zoho CRM Plus Resources

        Zoho Books Resources


          Zoho Subscriptions Resources

            Zoho Projects Resources


              Zoho Sprints Resources


                Zoho Orchestly Resources


                  Zoho Creator Resources


                    Zoho WorkDrive Resources



                      Zoho Campaigns Resources

                        Zoho CRM Resources

                        • CRM Community Learning Series

                          CRM Community Learning Series


                        • Tips

                          Tips

                        • Functions

                          Functions

                        • Meetups

                          Meetups

                        • Kbase

                          Kbase

                        • Resources

                          Resources

                        • Digest

                          Digest

                        • CRM Marketplace

                          CRM Marketplace

                        • MVP Corner

                          MVP Corner




                          Zoho Writer Writer

                          Get Started. Write Away!

                          Writer is a powerful online word processor, designed for collaborative work.

                            Zoho CRM コンテンツ




                              ご検討中の方