Dear all,
Zoho project is great but the dependencies is totally worthless.
It seems to me that the only way to remove a dependency is via the Dependency View and that view is really terrible. There must be a way to group the task by task list and milestone or at least apply a filtering to the list. It's impossible to find a task when you have hundreds within a project.
EDIT: Found a way to remove dependencies in the Gantt view. Great improvement for my workflow!
Also, if I wish to insert a task between two dependent task, the only way is to remove the dependency and then add it again using the new tasks. This would be OK if it was possible to do in the gantt view or if the dependency view was better.
Also, more dependencies need to be implemented (start-to-start, finish-to-finish).
As dependencies work now, they cause more trouble compared to their usefulness as editing tasks becomes a hassle (due to their dependencies) and editing dependencies is even more troublesome.
Please improve this ASAP.