A critical task or activity is a task that directly impacts the project's planned completion date. A one-day increase in the duration of a critical task will delay the project by one day.
What is a critical task?
A critical task or activity is a task that directly impacts the project's planned completion date. An increase in the duration of a critical task will delay the successor tasks and as a consequence, delay the project.