Dependency in Milestone Gantt Chart | Online Help | Zoho Projects

Dependency in Milestone Gantt

Set dependencies in the Milestone Gantt. Dependencies can be set within the same project or across different projects.
500 dependencies can be added in a single tree

Set Dependency Between Tasks of the Same Project

  1. Navigate to a project from the Recent Projects section or the Projects tab and select a project.
  2. Click Gantt & Reports in the top navigation panel.
  3. Select the Gantt Chart from the drop-down.

  4. Select Milestone Gantt from the drop-down in the right corner of the Gantt view.
  5. Mouse over the task name and click to open a pop-up box.
  6. Toggle between the Predecessors and the Successors tab, then click Add Predecessor or Add Successor.
  7. The Select Project drop-down will display the name of your current project. Enter the task name you want to link in the text box and select the task from the list.
  8. Click Set Dependency.


 Set Dependency Between Tasks Across Projects

  1. Navigate to a project from the Recent Projects section or the Projects tab and select a project.
  2. Click Gantt & Reports in the top navigation panel.
  3. Select the Gantt Chart from the drop-down.
  4. Select Milestone Gantt from the drop-down in the right corner of the Gantt view. 
  5. Mouse over the task name and click to open a pop-up box.
  6. Toggle between the Predecessors and the Successors tab, then click Add Predecessor or Add Successor.
  7. The Select Project drop-down will display the name of your current project. Enter the task name you want to link in the text box and select the task from the list.
  8. Click Set Dependency.

Set Task Dependency Using Milestone Gantt

  1. Navigate to a project from the Recent Projects section or the Projects tab and select a project.
  2. Click Gantt & Reports in the top navigation panel.
  3. Select the Gantt Chart from the drop-down.
  4. Select Milestone Gantt from the drop-down in the right corner of the Gantt view.
  5. Click and drag a line from the parent task to the target task in the Gantt chart. A dependency is created.


View Task Dependency on Milestone Gantt

  1. Navigate to a project from the Recent Projects section or the Projects tab and select a project.
  2. Click Gantt & Reports in the top navigation panel.
  3. Select the Gantt Chart from the drop-down.
  4. Select Milestone Gantt from the drop-down in the right corner of the Gantt view.
  5. Hover over the task name and click to open a pop-up box to view its task assignee, start date, end date, and predecessor/successor tasks in the task pop-up. Also perform other action like, 
  6. Click   to bring the task's corresponding Gantt to view. Also, click the icon and draw a line to the target task to set a new dependency. 
  7. Click to add a new task.
  8. Click and drag and drop the task to reorder. 

 Modify Task Dependency Type

  1. Navigate to a project from the Recent Projects section or the Projects tab and select a project.
  2. Click Gantt & Reports in the top navigation panel.
  3. Select the Gantt Chart from the drop-down.
  4. Select Milestone Gantt from the drop-down in the right corner of the Gantt view. 
  5. Mouse over the task name and click to open a pop-up box.
  6. Toggle between the Predecessors and the Successors tab to view linked tasks.
  7. Click near the current dependency to change it.
     

Remove Task Dependency

  1. Navigate to a project from the Recent Projects section or the Projects tab and select a project.
  2. Click Gantt & Reports in the top navigation panel.
  3. Select the Gantt Chart from the drop-down.
  4. Select Chronology Gantt from the drop-down in the right corner of the Gantt view. 
  5. Mouse over the task name and click to open a pop-up box.
  6. Toggle between the Predecessors and the Successors tab to view linked tasks.
  7. Hover over dependency and then click to remove dependency.

 Set Lag or Lead


Lag is the time gap between the predecessor and successor tasks. If the lag value is negative, it is known as lead time. Learn when to use lead and lag values.

  1. Navigate to a project from the Recent Projects section or the Projects tab and select a project.
  2. Click Gantt & Reports in the top navigation panel.
  3. Select the Gantt Chart from the drop-down.
  4. Select Chronology Gantt from the drop-down in the right corner of the Gantt view. 
  5. Mouse over the task name and click to open a pop-up box.
  6. Toggle between the Predecessors and the Successors tab to view linked tasks.
  7. Click Set time lag.
  8. Enter the lag value and click  to save.

See Also

    Redefine the way you work
    with Zoho Workplace

      Zoho DataPrep Personalized Demo

      If you'd like a personalized walk-through of our data preparation tool, please request a demo and we'll be happy to show you how to get the best out of Zoho DataPrep.

      Zoho CRM Training

        Create, share, and deliver

        beautiful slides from anywhere.

        Get Started Now


          Get started with Zoho Sign

          in a few quick steps!

          Download Help Guide





                       
                      Secure your business
                      communication with Zoho Mail


                      Mail on the move with
                      Zoho Mail mobile application

                        Stay on top of your schedule
                        at all times


                        Carry your calendar with you
                        Anytime, anywhere




                                Zoho Sign Resources

                                  Sign, Paperless!

                                  Sign and send business documents on the go!

                                  Get Started Now


                                      Zoho SalesIQ Resources



                                          Zoho TeamInbox Resources



                                                  Zoho DataPrep Resources



                                                    Zoho DataPrep Demo

                                                    Get a personalized demo or POC

                                                    REGISTER NOW


                                                      Design. Discuss. Deliver.

                                                      Create visually engaging stories with Zoho Show.

                                                      Get Started Now











                                                                            • Related Articles

                                                                            • Dependency in Chronology Gantt Chart

                                                                              Set dependencies in the Milestone Gantt. Dependencies can be set within the same project or across different projects. 500 dependencies can be added in a single tree Set Dependency Between Tasks of the Same Project Navigate to a project from the ...
                                                                            • Global Milestone Gantt

                                                                              Projects based Milestone Gantt shows a detailed view of the projects and their associated milestones in the Gantt chart. Feature Availability: Enterprise plan Benefits Keep track of all the milestones in a project. See overlapping activities and ...
                                                                            • Gantt Charts

                                                                              The Reports module in Zoho Projects shows a variety of data in terms of Gantt charts and reports for tasks, bugs, and timesheet to help you measure productivity and work progress effectively. Feature Availability: Editable Global Gantt charts: ...
                                                                            • Planned vs. Actual hours for tasks

                                                                              Planned vs Actual is a feature that indicates the work progress of the user based on the difference in their planned and actual hours. You can view both the total planned hours of a user and the actual hours spent by the user in a project. The ...
                                                                            • Task Dependency Settings

                                                                              Configure task dependency settings and set default dependency type. Move up or extend dates of successor tasks or reschedule them based on completion date of predecessor task. Benefits: Move up dates of successor tasks if the predecessor task moves ...
                                                                            Wherever you are is as good as
                                                                            your workplace

                                                                              Resources

                                                                              Videos

                                                                              Watch comprehensive videos on features and other important topics that will help you master Zoho CRM.



                                                                              eBooks

                                                                              Download free eBooks and access a range of topics to get deeper insight on successfully using Zoho CRM.



                                                                              Webinars

                                                                              Sign up for our webinars and learn the Zoho CRM basics, from customization to sales force automation and more.



                                                                              CRM Tips

                                                                              Make the most of Zoho CRM with these useful tips.



                                                                                Zoho Show Resources